Vivienne House


project details

Client:
Hutton Developments/Headoffice3
Project duration:

Phase 1: 6 Weeks & Phase 2: 20 Weeks

Year: 2018/19

Value:
£385,000

scope of works

Appointed by Headoffice3 on behalf of Hutton Developments in October 2018, work is currently underway to convert an empty office building into eight luxury apartments located in North London.

The accommodation on the ground and first floors provides six apartments with the conversion of the roof space providing a further two units.

The project consists of two distinct phases:

• Phase 1: Demolition and enabling works

• Phase 2: Conversion and fit-out works