Metropolitan Housing Trust – Clapham Park Estate Refurbishment
project details
- Client:
- Metropolitan Housing Trust
- Overview:
-
- Roofing , soffits, fascias and rainwater goods
- Internal & External Decorations
- Window Repairs/Replacement
- Brickwork and Concrete Repairs
- Light refurbishment works to external fabric of blocks of flats
- Kitchen & Bathroom Upgrades
- Electrical rewiring
- External hard and soft landscaping works to car parking areas, pedestrian walkways and common areas
- Project duration:
- 10 Months
- Value:
- £1.2m
scope of works
TCL were appointed in late 2015 to undertake external/internal repairs and improvements to a number of 1920’s built occupied blocks of flats located within the Clapham Park Estate.
The works commenced in December 2015 and completed in September 2016, one month ahead of programme.
Planning and the adoption of proven corrective measures enabled us to minimise access issues to enable the requirements of the programme to be maintained.
Related Case Studies












Tags: Painting and Decorating, Refurbishment and Heritage Works